Update 7-17-19

  • Things have really begun to come together during the past two weeks.  A new ceiling has been installed throughout the hallway in the main building, which was built in 1935. Under that ceiling, wires and cable have been installed to support the use of technology in all of our classrooms. A new door has been cut out of the cinder block in order to provide access to our state of the art World Language Lab. Meanwhile, new LED lighting and floors were installed in freshly painted classrooms. 

    Third floor construction Construction Third Floor Classroom

Update 7-3-19

  • The renovation of the third floor began on June 20, 2019.  Demolition is almost complete. In order to meet our timeline, we are addressing issues immediately as they arise, including ceiling replacement to meet fire code, abatement of previously unexposed asbestos in isolated areas, and removal of pipes that are no longer needed. The pictures include our third-floor corridor ready for a new ceiling and floor, our future bookroom, and the beginning of the World Language Lab.

    third floor          third floor   third floor

Construction Timeline

If you are having trouble viewing the document, you may download the document.